The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A.estimating B.defining C.planning D.sequencing
A.project scope statement B.project requirement C.project charter D.product specification
The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan B.contract C.project human resource plan D.projectcharter